Corbridge Crescent

Corbridge Crescent

Corbridge Crescent Key Project Info: Client: Aitch Group Value: £22m Dates of engagement: 2018 to 2019 Contractor: Havering Demolition Steve King of RAD acted as CEM for this project through the design and demolition and remediation phases, attending the design team...
540 Portswood Road

540 Portswood Road

540 Portswood Road Key Project Info: Client: Glenmore Student Property (Southampton) Ltd Value: Circa £40m Dates of engagement: 2019 to 2020 Contractor: Midas RAD were brought in by the client to advise on what works would require Network Rail approvals and to advise...
21 Moorfields

21 Moorfields

21 Moorfields Key Project Info: Client: Land Securities Value: £275m Dates of engagement: 2014 to 2016 Contractor: Keltbray and Mace Piling rig working from a temporary steel platform over the station roof 2.4m diameter piles are being bored to a depth of 60m to...
South Wimbledon Station

South Wimbledon Station

South Wimbledon Station In 2018/2019 Rail Asset Development were engaged by Clarion housing association to provide advice on the feasibility of a number of options for developing South Wimbledon Station and the surrounding High Path Estate redevelopment, which is...
Camden Lock Village

Camden Lock Village

Camden Lock Village   The duties undertaken included: Lead for all LUL and NR interface issues on both sites Network Rail Contractor’s Engineering Manager (CEM) and CRE Construction Proposed and agreed monitoring arrangements with NR and LUL Determined list of...