Oak Tree Gardens
Key Project Info:
- Client: P J Construction
- Value: Circa £1m
- Dates of engagement: 2018
- Contractor: P J Construction
- Rail Asset Development’s first project was assisting this local builder-developer with the rail interface on a development of six semi-detached units close to Sundridge Park station
- Planning restrictions meant that a 2m high contiguous retaining wall had to be constructed close to the toe of the railway embankment
The duties undertaken included:
- CEM and lead on the railway interface
- Identification and preparation of all required Network Rail submissions, negotiating the approvals needed
- Working with contractors unfamiliar with railway requirements to ensure that designs and RAMS were suitable for use adjacent to the operational railway