Camden Lock Village
The duties undertaken included:
- Lead for all LUL and NR interface issues on both sites
- Network Rail Contractor’s Engineering Manager (CEM) and CRE Construction
- Proposed and agreed monitoring arrangements with NR and LUL
- Determined list of required design and method deliverables and agreed with NR and LUL
- Compiled, reviewed and negotiated approval of temporary works submissions, including basement propping scheme
- Met NR and LUL regularly through design and delivery
- Negotiated agreements for excavations up to 15m deep and 5m from the railway viaduct
- Negotiated agreements for scaffolding 3.2m from the OLE
- Managed the development and delivery of rail-specific safety briefings for all general construction staff working on the site
- Developed a proposal for the removal of a section of NR viaduct known as the coal chute, which included relocating safety-critical rail assets
- Scoped, procured and managed the NR-specialist design and construction teams developing the coal chute design and delivering it
Key project info:
- Client: Stanley Sidings
- Value: £200m (main and school sites)
- Dates of engagement: 2015 to 2017
- Contractor: Mace (main site) and McLaughlin and Harvey (school)
- Complex multi-use site built around two Network Rail viaducts and alongside the two branches of the Northern Line