Bounds Green Depot
Key Project Info:
- Client: GNER
- Value: £2.7m
- Dates of engagement: 2010 to 2011
- Contractor: YJL Infrastructure
- New sidings and wheel lathe building and new depot plant for the adjoining existing buildings
- A boundary issue meant that the original scheme drawn up by the client could not be fitted on to the site. requiring extensive redesign
The duties undertaken included:
- Bid team lead and Contractor’s Engineering Manager for the delivery phase
- Worked with colleagues in a collaborative team to develop a new scheme meeting the client’s significant cost, programme and physical constraints
- Provided advice and support for the site team on aspects of the depot plant
- Achieved an overall saving of 25% on the construction costs