Bounds Green Depot

Key Project Info:
  • Client: GNER
  • Value: £2.7m
  • Dates of engagement: 2010 to 2011
  • Contractor: YJL Infrastructure
  • New sidings and wheel lathe building and new depot plant for the adjoining existing buildings
  • A boundary issue meant that the original scheme drawn up by the client could not be fitted on to the site. requiring extensive redesign
The duties undertaken included:
  • Bid team lead and Contractor’s Engineering Manager for the delivery phase
  • Worked with colleagues in a collaborative team to develop a new scheme meeting the client’s significant cost, programme and physical constraints
  • Provided advice and support for the site team on aspects of the depot plant
  • Achieved an overall saving of 25% on the construction costs